Table 6.3.1.3 - Inspection procedure and maintenance plan for electric parts
Items
Electric motor
Limit switch
Push-button switch box
and
cable
Start panel

6.3.2 On-board maintenance procedure

6.3.2.1 General
As a result of inspection, any defective parts should be repaired in accordance with fol-
lowing procedures. Any shortage of quantity should be supplemented to correct number.
Defective parts other than the followings should be recorded along with their details and
ordered for maintenance and repair by the manufacturers.

6.3.2.2 Wire rope

6.3.2.2.1 Wire ropes should be changed in the following cases: 6.3.2.2.2 Check fixing
condition of wire ropes.
.1 Break of elemental wire was observed;
.2 7% reduction of nominal diameter was observed;
.3 Kink or looseness of ply was observed; or
.4 Erosion / corrosion was observed.
6.3.2.2.3 Change the boat falls within an appropriate period.
6.3.2.2.4 Adjust the length of boat falls as necessary so that the clearances between the
davit arm and davit arm stopper at fore and aft are almost the same.
6.3.2.2.5 Ensure that material and diameter of suspension links are as specified by the re-
lease gear manufacturer.
Method
Inspection procedure
Visual
Check wiring.
Operation
Check normal operation.
Visual
Check wiring.
Operation Check normal operation.
Lubricate
Lubricate/grease.
Check wiring and other de-
Visual
fects.
Operation Check normal operation.
Check wiring and other de-
Visual
fects.
Operation
Check normal operation.
Maintenance
plan
Weekly Monthly
X
X
X
X
X
X
X
X
X
X
X
X
X