SB Flat Installation Manual
2. Check Installation environment
7. Check needle bar upper dead/needle drop point
9. Machine motion test and running test.
SUNSTAR Co.Ltd
Contents
(1) Checking Machine Exterior
(2) Assemble Spool Stand
Page 1 Of 11
SWF CS Center

Advertisement

loading
Need help?

Need help?

Do you have a question about the SB Flat and is the answer not in the manual?

Questions and answers

Summary of Contents for SWF SB Flat

  • Page 1: Table Of Contents

    SB Flat Installation Manual Contents 1. Check installation tools 2. Check Installation environment 3. Check and adjust levelness 4. Assembly (1) Checking Machine Exterior (2) Assemble Spool Stand 5. Runing Test 6. Check and adjust needle drop position 7. Check needle bar upper dead/needle drop point 8.
  • Page 2: Check Installation Tools

    - Adjust Input Voltage if it is different from M/C Specification. - It shoud be around 120V in case of ground if machine is 220V in picture 3. Picture 1 Picture 2 Picture 3 SUNSTAR Co.Ltd Page 2 Of 11 SWF CS Center...
  • Page 3: Check And Adjust Levelness

    Height Equipment. Side (Right) Side (Left) At the point marked by O, level the height of water and body to be within 0.5mm error range. Level front/rear within the range. Bolt SUNSTAR Co.Ltd Page 3 Of 11 SWF CS Center...
  • Page 4: Assembly

    ① Insert the spool stand to the spool stand stud bolt. (Insert spool stand "A" to the thread tension plate) ② Fix thread holder angle "D" to the angle base. (Use M4L10 bolt to fix) SUNSTAR Co.Ltd Page 4 Of 11 SWF CS Center...
  • Page 5: Runing Test

    2) If it is not proper, reset it in middle needle bar and then check first and last needle bar. (1) In case that needle drop position is in left and right SUNSTAR Co.Ltd Page 5 Of 11 SWF CS Center...
  • Page 6 ※ Head Rail Spec. manufactured for E&K Tubular -> 4.4 T (4) In case that needle drop position is in rear - Insert Head Rail Gauge between Head and Head Rail. ※ Types of Head Rail Gauge → 0.1T, 0.2T, 0.3T SUNSTAR Co.Ltd Page 6 Of 11 SWF CS Center...
  • Page 7 Lightly hold upper dead point stopper and shake up/down to check for looseness/gap. Looseness/gap may cause needle bar to not move properly. Do not push up too much and do not allow looseness/gap when setting. (This may cause noise when SUNSTAR Co.Ltd Page 7 Of 11 SWF CS Center...
  • Page 8: Check And Adjust Rotary Hook Timing

    Lock all rotary hook Screws. Needle Point of Rotary Hook Rotary Hook Support Projection Part in Rotary Hook Support should be in Set Gap (0.1~0.3mm) the center of Needle. - Set Gap (0.5~0.7mm) from Hook. SUNSTAR Co.Ltd Page 8 Of 11 SWF CS Center...
  • Page 9: 10 Embroidery Test

    ※When running an embroidery test, train the staff and administrator from a client company on machine control and maintenance. ※Refer to, and follow directions in, installation manual and installation check list. SUNSTAR Co.Ltd Page 9 Of 11 SWF CS Center...
  • Page 10 Machine TEST after Installation (1) JUMP TEST Pass Fail (2) WIPER TEST Pass Fail (3) PICKER TEST Pass Fail (4) TRIM TEST Pass Fail (5) THREAD SENSING TEST Pass Fail Check Needle Drop Position Page 10 Of 11 (주) SUNSTAR SWF CS Center...
  • Page 11 Write productivity result report. Attach original design and the work sample to the report. ※When running an embroidery test, train the staff and administrator from a client company on machine control and maintenance. Page 11 Of 11 (주) SUNSTAR SWF CS Center...