Page 1
Gocycle Service Notice 8.0: Battery Installation OCYCLE ERVICE OTICE IGHLY WITHOUT SERVICE ACTION COMPONENT IGHLY ECOMMENDED DAMAGE CAN OCCUR ECOMMENDED Battery Installation Service Issue Frame numbers affected: All Installing the battery pack for the first time can be challenging due to the internal cables in the frame being in a ‘relaxed’...
Page 2
Gocycle Service Notice 8.0: Battery Installation Look inside the battery aperture in the frame. The picture below shows the cables in a ‘relaxed’ state making it very difficult to install the battery pack. Cables can be ‘relaxed’ and bunched up, which can make it hard to insert the battery pack.
Page 3
Gocycle Service Notice 8.0: Battery Installation Notice how the cables are now tightened inside the frame. This will allow the battery to be installed easily. This shows the cables now ‘tightened’ and out of the way of the battery pack.
Need help?
Do you have a question about the G1 and is the answer not in the manual?
Questions and answers