Chapter 3: Installing the Transmitter
Whenever possible, separate your instrumentation wiring from other wiring by using a
l
separate metal conduit or metal wire tray.
Use the minimum length of cable required for the installation and cut off any excess. Do
l
not coil excess wire.
For longer runs (maximum 1,000 feet) use #22 AWG shielded twisted pair cable for signal
connections, and tie the shield to the ground at the receiving device, not at the TRICON/E
transmitter.
When forced to cross other wiring, cross at right angles to minimize noise coupling
l
between wiring.
Use a dedicated power source, such as a separate circuit breaker or isolation transformer,
l
for all instrumentation equipment to reduce the effects of electrical noise from other
equipment on the line.
Ensure proper earth ground is available and installed in compliance with local electrical
l
codes.
Installation
This section defines the procedures to install the TRICON transmitter.
Wiring the Transmitter
Follow this procedure to wire the transmitter.
1. Locate the terminal cover and remove the cover screw.
2. Lift the terminal cover from the transmitter.
10
Figure 1 – Transmitter Elements
TRICON ® E/E2/E3 Installation and Maintenance Guide