Finally; General; Visual Inspection - Fronius Primo 208-240 Service Manual & Spare Parts List

Inverter for grid-connected photovoltaic systems
Hide thumbs Also See for Primo 208-240:
Table of Contents

Advertisement

Available languages

Available languages

Finally...

General

-
-
-
-
-

Visual Inspection

Deficiencies identified that may be the cause of other hazards must be repaired immedi-
ately, otherwise further use must be restricted until the defect is rectified.
-
-
-
-
Isolate the inverter in its unloaded state from the AC grid and the DC power supply (set
DC disconnector to level 0).
Refit and attach all removed Datcom lines (restore inverter to original state prior to the
repair or safety inspection).
If necessary, reinstall the AC lead in the PG screw joint.
Check whether conductive objects are deposited in the housing.
Mount Datcom lid with 4 screws 5x16 TX25 – 2 Nm
Missing or damaged housing parts, insulating parts, or protective covers.
Soiling and blockage of cooling vents.
Check that safety labels are present (such as warning notices, grounding symbols, rat-
ing plates) and replace, supplement, or correct if necessary.
Ensure that all safety-related labels or symbols, rated values and position indicators
are legible.
155