Red Flash The
After finishing the above steps, please wait for initialization.
Close AC input side circuit breaker, waiting for about 1~2 seconds till
Power Pack power indicator light, check whether the Solar Pumping
Inverter power led and its LCD are light or not. If only turn on DC input
side circuit breaker, and Power Pack indicator is not lit, you can check
whether the input side is normal or not through Solar Pumping Inverter.
Warning!
If the power indicator of Power Pack is light after turning on the AC input
circuit breaker, while the Solar Pump Inverter power led and the LCD are
not lit; checking whether the DC switch of the Solar Pump Inverter is on
or off. If the DC switch is off, the circuit breaker of the AC side should be
disconnected first till the the power indicator of the Power Pack turned
off, turn on the DC switch of the Solar Pump Inverter. Reconnect the AC
side circuit breaker of Power Pack.
Do not turn on the DC switch of the Solar Pump Inverter directly
when the Power Pack power indicator is lit ! ! !
At this point, the commissioning of Power Pack is finished.
voltage
overheat/Temperature sensor fault,
Utility Grid Power is withdrawn.