Commissioning

5.2 Commissioning
5.2
Commissioning
Requirements
Ensure that the following commissioning conditions are being met:
• You have connected the sensors correctly. For additional information, refer to:
– Connecting the resistance thermometer (Page 27)
– Connecting the thermocouple (Page 28)
• Ensure that the electrical connections are tightened with the correct torque.
• The following applies in particular for device versions with explosion protection:
– Ensure that the cable glands are suitable for the process and have been tightened
– The electrical data must match the specified ex-relevant values.
• All seals must be present, placed correctly and undamaged.
Procedure
1. Close the connection head. Fully screw on the cover for device versions with flameproof
enclosures.
2. Connect the sensor integrated into the process to the power supply.
32
correctly.
SITRANS TS100/TS200/TS300/TS500/TSinsert/TSthermowell
Compact Operating Instructions, 08/2020, A5E03920348-AF