Scenario 2: Routing Cables from the Bottom
1. Remove the cable covers from the bottom of
the cabinet, drill holes in the covers, attach
grommet strips to the hole edges for
protecting cables, and reinstall the cable
covers.
2. Connect power cables and signal cables.
For the screw specifications and torque
used for connecting cables in a bottom
cable routing scenario, refer to the top
cable routing scenario. This section only
shows the cable routes in the bottom cable
routing scenario.
4

Verifying the Installation

1. Check that there is no foreign matter in the cabinet.
2. After verifying the installation, reinstall all
the covers.
3. (Remove the paper protective film from the
sealing putty.) After routing cables and
verifying cable connections, seal the gap
between cables and the cabinet using
sealing putty.
Sealing putty must be used as a whole and
the gap can be sealed only from the top.