I. PRELIMINARY INFORMATION
MODEL NO.:
DATE:
II. PRE-START-UP (insert checkmark in box as each item is completed)
REMOVE ALL SHIPPING HOLDDOWN BOLTS AND BRACKETS PER INSTALLATION
INSTRUCTIONS
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED AS SHOWN IN THE
INSTALLATION INSTRUCTIONS
CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
CHECK THAT INDOOR-AIR FILTERS ARE CLEAN AND IN PLACE
VERIFY THAT UNIT INSTALLATION IS LEVEL WITHIN TOLERANCES LISTED IN THE
INSTALLATION INSTRUCTIONS
CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND
SETSCREW TIGHTNESS
CHECK PULLEY ALIGNMENT AND BELT TENSION; REFER TO INSTALLATION
INSTRUCTIONS
III. START-UP:
ELECTRICAL
SUPPLY VOLTAGE
COMPRESSOR AMPS
INDOOR-FAN AMPS
TEMPERATURES
OUTDOOR-AIR TEMPERATURE
RETURN-AIR TEMPERATURE
COOLING SUPPLY AIR
PRESSURES
REFRIGERANT SUCTION
REFRIGEANT DISCHARGE
VERIFY REFRIGERANT CHARGE USING COOLING CHARGING CHARTS ON
PAGES 27 AND 28.
VERIFY THAT 3-PHASE SCROLL COMPRESSOR IS ROTATING IN CORRECT DIRECTION
(PA1R072 SCROLL ONLY)
Copyright 1998 Payne Heating & Cooling, Indianapolis, IN
START-UP CHECKLIST
(Remove and Store in Job File)
L1-L2
L2-L3
L1
L2
L1
L2
DB
DB
PSIG
PSIG
SERIAL NO.:
TECHNICIAN:
L3-L1
L3
L3
WB
CL-1
CATALOG NO. 53PA-1R0