Installing an RTN 360
1
Installing an RTN 360 at the Edge of a Mobile Backhaul Network
Installation procedure
1
Install the ground cable.
2
Install an RTN 360 on a pole or wall.
Connect one end of an outdoor network cable to port
3
P&E on the RTN 360 and lay out the cable.
Power over ethernet supports a maximum distance of 100
meters.
Commissioning procedure
4
Connect the other end of the outdoor network cable to the
P&E port on the PI to power on the RTN 360.
A GE port on the PI connects to the peer
wireless device. For details about how to install
a PI and cables, see the OptiX RTN PI-AC B20
Product Overview and Installation Guide.
Load commissioning data to the RTN 360 using the
5
Web LCT.
Align the RTN 360 with its peer.
6
Ensure that the received signal level (RSL) of
7
the RTN 360 is consistent with the network
plan.
8
Verify the installation.
10/11 >>
Optional: Install the
RTN 360 on a pole.
2
Optional: Install the
RTN 360 on a wall.
GE1
P&E1
B20 PI
4
To the wireless
equipment at the
opposite end
To the RTN 360
RTN 360
2
1
4
Clip
External power
supply equipment
Optional: In this example, port GE(e) is
not used. In practice, determine whether
to use this port based on your service
plan.
In this example, the RTN 360 uses port
P&E to receive services and power
signals.
3
Wireless equipment at the
opposite end
1
Instal

Advertisement

Table of Contents
loading

Table of Contents