Step 11 Connecting The Power And Communication Cables - Samsung AM093MNQDEH Installation Manual

Table of Contents

Advertisement

Step 11 Connecting the power and
communication cables
Before wiring work, you must turn off all power
1
source.
2
Indoor unit power should be supplied through the
breaker( ELCB or MCCB+ELB ) separated by the
outdoor power.
• ELCB:Earth Leakage Circuit Breaker
• MCCB:Molded Case Circuit Breaker
• ELB:Earth Leakage Breaker
3
The power cable should be used only copper wires.
4
Connect the power cable{1(L), 2(N)} among the units
within maximum length and communication cable(F1,
F2) each.
7
Connect F3, F4(for communication) wires at the back side of the indoor unit when installing the wired remote control.
Outdoor Unit
220-240V~or
MCCB+
ELB
ELCB
Indoor Unit 1
• ELCB : Essential Installation
• The EEV Kit is optional component.
WARNING
• Power off before connecting any wires;Indoor PBA will be damaged while V1,V2,F3,F4 short each other.
• You must connect the earth cable. If earthing is not complete, electric shock or fire may occur.
Indoor Unit 2
Indoor Unit 3
5
Cut the cable as like the following picture. The earth
cable need to be longer than the power cable (1(L),
2(N)) by 100 mm.
6
Connect the earth cable to the plate on the evaporator
as like the following picture.
Power-earth
cable
Wired Remote
Control
V1 V2
Indoor Unit 4
Ceiling, wall-mounted indoor unit.
100mm
EEV kit
N
L
N
L
N
L
Indoor Unit 5
Indoor Unit 6
English
11

Advertisement

Table of Contents
loading

Table of Contents