5.4 Handover
Open the transformer package and immediately check for damage during transport. In case of damage, please claim
compensation against the carrier and ask the representative of Siemens to coordinate this issue if necessary. Report the
damage to Siemens through the Siemens representative who is in charge of such matters.
Please refer to the following steps to check the transformers delivered on site with the carrier and make
relevant records.
a. Check the outer packing of the transformer, such as wooden box and the plastic hood, which shall be in good condition.
b. Check the transformer model and the quantity and documentation, which shall be correct and complete according to the
order.
c. Check the appearance of transformer protective enclosure, such as door panel, base and other components, which shall be
complete and free of damage.
d. Check the appearance of transformer body, such as winding, copper bar and other parts, which shall be complete and free
of damage.
5.5 Storage
If not installed immediately, the transformer needs to be stored in a dry room to avoid direct sunlight. Indoor temperature shall
not be less than minus 25 º C (unless otherwise agreed) and humidity shall not exceed 90%. It shall be covered properly to
prevent rain, dew and dust contamination.
Storage requirements:
a. Storage temperature-25 ºC ~ 50 ºC, humidity ≤ 90%. Installation and
storage of transformers below-25 ºC is prohibited (unless otherwise
specified in the agreement).
b. It shall be covered with opaque materials to prevent damaging the
transformer due to dampness, water, dust and sunlight.
c. The warehouse shall be cleaned, dried and ventilated and
transformers shall not be stored together with active chemicals and
corrosive substances.
d. Stacking in warehouse is not allowed for all products.