WARNING! It is imperative that L1, L2, and L3 in the
starter be connected in the A-BC phase sequence to
prevent equipment damage due to reverse rotation.
WARNING!To prevent injury or death due to
electrocution, take extreme care when performing service
procedures with electrical power energized.
CAUTION! Do not interchange any load leads that are
from the unit contactors or the motor terminals. Doing so
may damage the equipment.

Water System Flow Rates

Establish a balanced chilled-water fl ow through the
evaporator. The fl ow rates should be between the
minimum and maximum values given on the pressure
drop curves.

Water System Pressure Drop

Measure the water-pressure drop through the evaporator
on the fi eld installed pressure taps on the system water
piping. Use the same gauge for each measurement. Do
not include valves, strainers, or fi ttings in the pressure
drop readings.
Integrated Pump Package (Optional)
Before starting up the pump, the pipe system must be
thoroughly cleaned, fl ushed and fi lled with clean water.
Do not start the pump until it has been vented. To ensure
correct venting, open the vent screw located on the pump
housing on the suction side (see next fi gure).
CAUTION! When using freeze inhibitor, never fi ll the
system with pure glycol; this will damage the shaft seal.
Always fi ll the system with diluted solution. Maximum
concentration of glycol is 45% for unit with pump
package.
If the chiller is installed in a humid environment or a
location with high air humidity, the bottom drain hole on
the pump motor should be opened. The enclosure class of
the motor is then changed from IP55 to IP44. The function
of the drain holes is to drain off water which has entered
the stator housing with air humidity.
Figure 23 – Pump Package
B
C
C
A = Pump vent screw
B = Air vent valve
C = Drain valve
RLC-SVX19A-E4
F
B
A
F
A
E
E
D
D= Drain and fi ll valve
E = Pump drain plug
F = Motor drain hole plug
Expansion Tank
(Pump Package Option)
The factory installed expansion tank initial pressure
should be adjusted about 0.5 bars higher than the static
pressure applied to the chiller water inlet. The static
pressure is given by the maximum water circuit height
compare to chiller location: example: the chiller is at
ground level and the circuit loop goes from basement
(at -4m compare to chiller) to third fl oor at 10 metres
above ground, the static pressure to use is 10 metres
of water (1 Bar) and the expansion tank initial pressure
should be 1.5 bars.
The expansion tank volume has been selected for
typical loop volume. The following table summarizes the
maximum volume of the chilled water loop that can be
supported by the expansion tank at different conditions.
If this maximum volume versus the required volume of
the installation is not enough, it will be necessary to add
an additional expansion tank located on the low pressure
side of the installation.
Table 24 – Maximum water loop volume in function of
static pressure
RTAF 090 to 205
Static pressure
Pure water
Ethylene glycol 20%
Ethylene glycol 30%
Ethylene glycol 45%
Tracer UC800 Set-Up
Using Tracer TU service tool, adjust the settings. Refer to
Tracer TU manual and UC800 user guide for instruction
on settings.
CAUTION! To prevent compressor damage, do not
operate the unit until all refrigerant valves and oil-line
service valves are opened.
IMPORTANT! A clear sight glass alone does not mean
that the system is properly charged. Also check system
discharge superheat, approach temperature and unit
operating pressures.
Pre-Start Checkout
1 Bar
2 Bar
3 Bar
6342
3996
1370
3409
2148
736
2273
1432
491
1515
955
327
47

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rtaf xe seriesRtaf hse seriesRtaf he series

Table of Contents