3.7 CHECKS FOLLOWING
CONVERSION TO ANOTHER TYPE
OF GAS.
After making sure that conversion was carried
out with a nozzle of suitable diameter for the
type of gas used and the settings are made at the
correct pressure, check that the burner flame is
not too high or low and is stable (does not detach
from burner);
Note: all boiler adjustment operations must be
carried out by a qualified company (e.g. Author-
ised After-Sales Assistance).
Id
Parameter
Parameter
Minimum DHW
S0
output
Maximum DHW
The boiler also has electronic modulation that adapts the boiler potentiality
S1
output
to the effective heating demand of the house. Therefore the boiler works
normally in a variable gas pressure field between minimum and maximum
power depending on the system heat load, setting fan speed (in rpm, hun-
dreds of revs are represented on the display).
N.B.: the boiler is produced and calibrated in the central heating phase at
nominal output. Approximately 10 minutes are needed to reach the nominal
heat output, which can be changed using the parameter (S3).
Minimum CH
S2
N.B.: selection of parameters in the presence of requests, allows boiler
output
functioning with current equal to the respective value.
Maximum CH
S3
output
Power
S4
block
Central heating
set point mini-
S5
Defines the minimum flow temperature.
mum tempera-
ture
Central heating
set point maxi-
S6
Defines the maximum flow temperature.
mum tempera-
ture
If the reading of the external probe is not correct it is possible to correct it
External probe
in order to compensate any environmental factors.
S7
correction
(Over the value of +9 the display shows "CE", which enables an external con-
trol function of the boiler for coupling of the same with a system supervisor)
Identifies the boiler's power (only useful with a coupled storage tank and
S8
Boiler power
parameter P0=1).

3.8 PROGRAMMING THE P.C.B.

The boiler is prepared for possible programming
of several operation parameters. By modifying
these parameters as described below, the boiler
can be adapted according to specific needs.
To access the programming phase, position
the DHW selector (5) on position "6", the CH
selector (6) on position "9" and press the "Reset"
(3) and "Summer/Winter" buttons for about 8
seconds (2).
Once the menu has been accessed, it is possible
to scroll through the three sub-menus present
(s, p, t) by pressing the "Summer/Winter" (2)
button for 1 second.
Description
29
Use the "DHW regulator" selector (5), to select
the parameter (inside the same sub-menu) and
rotate the "CH regulator" selector (6) to modify
the value according to the range available.
Press the "Reset" button (3) for 1 second to
memorise the variation of the parameters
Memorisation is represented via "88" on the
indicator (14) for 2 seconds.
Exit the programming mode by waiting for
15 minutes or by pressing the, "Reset" (3) and
"Summer/Winter" (2) buttons simultaneously.
Range
Default
Victrix Exa
28 1ErP=1400
900 ÷ 1500
Victrix Exa
32 1ErP=1200
28 1ErP
G20 = 5300
G30 = 4900
G31 = 5300
G25 = 5300
G27 = 5300
3500 ÷ 6100
32 1ErP
G20 = 4050
G30 = 3700
G31 = 4050
G25 = 4050
G27 = 4050
Victrix Exa
28 1ErP=1400
S0 ÷ S3
Victrix Exa
32 1ErP=1200
Victrix Exa
28 1ErP=4600
S2 ÷ S1
Victrix Exa
32 1ErP=3600
Victrix Exa
28 1ErP=2000
1500 ÷ 3500
Victrix Exa
32 1ErP=2300
20 ÷ 50 °C
25
(S5+5) ÷
85
85 °C
-9 ÷ 9 K
0
0 = 12 kW
1 = 26 kW
1
2 = 28 kW
3 = 32 kW