Sealing Cabinet To Floor - True TBR Series Installation Manual

Hide thumbs Also See for TBR Series:
Table of Contents

Advertisement

TRUE
TBR | TDR SERIES
INSTALLATION

SEALING CABINET TO FLOOR

STEP 1 – POSITION CABINET
the wall and rear of the refrigerated bar equipment to assure
proper ventilation.
STEP 2 – LEVEL CABINET
and front to back. Place a carpenter's level on the interior floor in
four places:
Position level in the inside floor of the unit near the doors
A.
(level should be parallel to cabinet front). Level cabinet.
Position level at the inside rear of cabinet (again, level should
B.
be placed parallel to cabinet back). Level cabinet.
. Perform similar procedures to Steps A & B by placing the
C
level on inside floor (left and right side, parallel to the depth
of the cooler). Level cabinet.
– Draw an outline of the base on the floor.
STEP 3
– Raise and block the front side of the cabinet.
STEP 4
STEP 5
– Apply a bead of NSF approved sealant (see list below)
to the floor, 1/2" (12.7 mm) inside the outline drawn. The bead
must be heavy enough to seal the entire cabinet surface when
it is down on the sealant.
– Raise and block the rear of the cabinet
STEP 6
– Apply sealant on floor as outlined in Step 5 on other
STEP 7
three sides.
– Examine to see that cabinet is sealed to floor around
STEP 8
entire perimeter.
Asphalt floors are susceptible to chemical attack. A layer
NOTE:
of tape on the floor prior to applying the sealant will
protect the floor.
NSF APPROVED SEALANTS:
Minnesota Mining #ECU800 Caulk
1.
Minnesota Mining #ECU2185 Caulk
2.
Minnesota Mining #ECU1055 Bead
3.
Minnesota Mining #ECU1202 Bead
4.
Armstrong Cork – Rubber Caulk
5.
Products Research Co. #5000 Rubber Caulk
6.
G.E. Silicone Sealer
7.
Dow Corning Silicone Sealer
8.
6
(CONT.)
– Allow 1" (25.4 mm) between
– Cabinet should be level, side to side