Page 1
Keysight Second Source, Combiner, and Mechanical Switches Upgrade Kit To Upgrade PNA-X N5241A, N5242A, or N5249A Option 219 to Option 224 For Analyzers with Serial Numbers Prefixed MY/SG/US5150 and Below Upgrade Kit Order Numbers: N5241AU-922, N5242AU- 922, N5249AU- 922 Keysight Kit Number: N5242-60102...
Page 3
Keysight Second Source, Combiner, and Mechanical Swithces Upgrade Kit Keysight Kit Number: N5242-60102 Installation Note Description of the Upgrade This upgrade kit is only for analyzers with serial numbers prefixed MY/SG/US5150 and below. If the serial number prefix of your analyzer is above this number, do NOT proceed with the upgrade.
Description of the Upgrade Getting Assistance from Keysight Getting Assistance from Keysight By internet or phone, get assistance with all your test and measurement needs. Contacting Keysight Assistance with test and measurements needs and information on finding a local Keysight office are available on the Web at: http://www.keysight.com/find/assist If you do not have access to the Internet, please contact your Keysight field engineer.
Description of the Upgrade Getting Prepared Getting Prepared The PNA contains extremely sensitive components that can be ruined if mishandled. Follow instructions carefully when making cable connections, especially wire harness connections. The person performing the work accepts responsibility for the full cost of the repair or replacement of damaged components.
Page 6
Description of the Upgrade Getting Prepared — From your instrument (Instrument information is available in the network analyzer – on the toolbar, click Help, then click About Network Analyzer.) — Model number — Serial number Using the information just gathered, you must request a license key from the Keysight Software Manager.
Description of the Upgrade Getting Prepared Tools Required for the Installation Description Part Number T-10 TORX driver (set to 9 in-lbs) T-20 TORX driver (set to 21 in-lbs) 5/16-in torque wrench (set to 10 in-lbs) 5/16-in torque wrench (set to 21 in-lbs) Use a 5/16-in torque wrench set to 10 in-lbs on all cable connections except the front and rear panel cable connectors.
Page 8
Items Included in the Upgrade Kit Items Included in the Upgrade Kit Check the contents of your kit against the following list. If any part is missing or damaged, contact Keysight Technologies. Refer to “Getting Assistance from Keysight” on page...
Page 9
Description of the Upgrade Items Included in the Upgrade Kit Table 1 Contents of Upgrade Kit N5242-60102 Description Part Number Desig. RF cable, W7 (from A8 26.5 GHz source 2) to front-panel SRC 2 OUT 2 N5242-20291 RF cable, W3 (from A5 26.5 GHz source 1) to A46 port 1 mechanical switch N5242-20269 RF cable, A46 port 1 mechanical switch to A25 test port 1 bridge N5242-20264...
Description of the Upgrade Installation Procedure for the Upgrade Installation Procedure for the Upgrade The network analyzer must be in proper working condition prior to installing this option. Any necessary repairs must be made before proceeding with this installation. This installation requires the removal of the analyzer’s protective outer covers.
Page 11
Description of the Upgrade Installation Procedure for the Upgrade Step 1. Obtain a Keyword and Verify the Information Follow the instructions on the Software Entitlement Certificate supplied to obtain a license key for installation of this upgrade. Refer to “License Key Redemption”...
Page 12
Description of the Upgrade Installation Procedure for the Upgrade Figure 1 Outer Cover Removal Step 3. Remove the Inner Cover Refer to Figure 2 for this step of the procedure. ① 1. With a T-10 TORX driver, remove the 12 pan head screws (item ➁...
Description of the Upgrade Installation Procedure for the Upgrade Figure 2 Inner Cover Removal Step 4. Remove the Front Panel Assembly Refer to Figure 3 for this step of the procedure. ① 1. With a 5/16-in wrench, remove all front panel jumpers (item ➁...
Page 14
Description of the Upgrade Installation Procedure for the Upgrade ③ 4. Disconnect the front panel interface ribbon cable (item ). The front panel is now free from the analyzer. Figure 3 Front Panel Assembly Removal Step 5. Remove the Existing Test Set Cables Leave the gray flexible cables, the wire harnesses, and the ribbon cables connected where possible.
Page 15
Description of the Upgrade Installation Procedure for the Upgrade For analyzers with serial numbers prefixed MY/SG/US5310 and below: — W25A28 port 2 bridge to front-panel REF 2 SOURCE OUT Figure 4 Existing Test Set Cables Removal Step 6. Assemble the Mechanical Switches Refer to Figure 5 for this step of the procedure.
Page 16
Description of the Upgrade Installation Procedure for the Upgrade Figure 5 Mechanical Switches Assembly Step 7. Install the Mechanical Switches Refer to Figure 6 for this step of the procedure. New parts are listed in Table 1 on page 1. Position the switch brackets (with the switches and combiner attached) in the analyzer as shown.
Page 17
Description of the Upgrade Installation Procedure for the Upgrade Figure 6 Mechanical Switches Installation into the Analyzer Step 8. Install the Second Source Boards Part 1: Install Cables on Second Source Boards Refer to Figure 7 Figure 8 for this step of the procedure. New parts are listed in Table 1 on page Installation Note N5242-90003...
Page 18
Description of the Upgrade Installation Procedure for the Upgrade 1. Attach gray flex cable W57 to the J5 connector on the A13 13.5 GHz synthesizer board as shown. The other end of the cable will be connected to the A10 frequency reference board later. Figure 7 Cable Connections to the Second Source Boards, Part 1a 2.
Page 19
Description of the Upgrade Installation Procedure for the Upgrade Figure 8 Cable Connections to the Second Source Boards, Part 1b Part 2: Install the Second Source Boards into the Analyzer Refer to Figure 9 for this part of this step of the procedure. New parts are listed Table 1 on page 1.
Page 20
Description of the Upgrade Installation Procedure for the Upgrade 3. Connect the other end of gray flex cable W57 on the A13 13.5 GHz synthesizer board to the J7 connector on the A10 frequency reference board as shown. 4. Connect cable W2 between the A8 26.5 GHz source 2 board and the A13 13.5 GHz source 2 synthesizer board as shown.
Page 21
Description of the Upgrade Installation Procedure for the Upgrade Figure 9 Second Source Boards Installation, Part 2 Step 9. Install the Source 2 Front Panel Connectors Refer to Figure 10 for this step of the procedure. New parts are listed in Table 1 on page ①...
Page 22
Description of the Upgrade Installation Procedure for the Upgrade Figure 10 Source 2 Front Panel Connectors Installation Step 10. Remove the A19 Test Set Motherboard and the A20 IF Multiplexer Board Remove the A19 Test Set Motherboard Refer to Figure 11 for this part of this step of the procedure.
Page 23
Description of the Upgrade Installation Procedure for the Upgrade ① ➁ 1. Disconnect ALL ribbon cables (item ) and ALL wire harnesses (item from the A19 test set motherboard. Make sure they are labeled for re-connection later. ③ 2. Remove connector hardware (item ) from 11 rear panel BNC connectors.
Page 24
Description of the Upgrade Installation Procedure for the Upgrade ➁ 2. Disconnect ALL gray flexible RF cables (item ) from the A20 IF multiplexer board. Make sure they are labeled for re-connection later. ③ 3. Remove connector hardware (item ) from five rear panel RF connectors. ④...
Page 25
Description of the Upgrade Installation Procedure for the Upgrade — SRC 2— SW SRC OUT (J8) — PORT 3—SW TSET IN (J7) — PORT 2—SW TSET IN (J1) and SW SRC OUT (J2) Refer to Figure 13 for this part of this step of the procedure. New parts are listed in Table 1 on page ①...
Page 26
Description of the Upgrade Installation Procedure for the Upgrade Step 12. Install the Bulkhead Connectors in the Test Set Front Plate Refer to Figure 14 for this procedure. Some bulkhead connectors may already be installed on your analyzer’s front plate. New parts are listed in Table 1 on page 1.
Page 27
Description of the Upgrade Installation Procedure for the Upgrade Install the following cables in the order listed. Use a 5/16-in torque wrench set to 10 in-lbs to tighten all cable connectors. — W95 (N5242-20269) A46 port 1 mechanical switch (connector 2) to W3 (from A5 26.5 GHz source 1 board) —...
Page 28
Description of the Upgrade Installation Procedure for the Upgrade Figure 15 New Test Set Cable Installation Installation Note N5242-90003...
Page 29
Description of the Upgrade Installation Procedure for the Upgrade Step 14. Reinstall the A20 IF Multiplexer Board and the A19 Test Set Motherboard Reinstall the A20 IF Multiplexer Board Refer to Figure 16 for this part of this step of the procedure. 1.
Page 30
Description of the Upgrade Installation Procedure for the Upgrade Figure 16 A20 IF Multiplexer Board Reinstallation Reinstall the A19 Test Set Motherboard Follow instructions carefully when making cable connections, especially wire harness connections. Incorrect connections can destroy components, resulting in additional customer costs. Refer to Figure 17 for this part of this step of the procedure.
Page 31
Description of the Upgrade Installation Procedure for the Upgrade ④ ⑤ 6. Reconnect ALL ribbon cables (item ) and ALL wire harnesses (item ) to the A19 test set motherboard. 7. Connect the mechanical switch control cables to the A19 test set ⑥...
Page 32
Description of the Upgrade Installation Procedure for the Upgrade 5. Starting from either side, loosely place the overlay in the recess on the lower front panel, ensuring that it fits tightly against the edges of the recess. 6. Once the overlay is in place, press it firmly onto the frame to secure it. Figure 18 Lower Front Panel Overlay Replacement Installation Note N5242-90003...
Page 33
Description of the Upgrade Installation Procedure for the Upgrade Step 16. Reinstall the Front Panel Assembly and Front Panel Jumpers Before installing the front panel assembly onto the analyzer, lift and support the front of the analyzer chassis. Refer to Figure 19 for this step of the procedure.
Page 34
Description of the Upgrade Installation Procedure for the Upgrade Step 17. Position the Cables and Wires to Prevent Pinching On the top side of the PNA, carefully position the grey flex cables so they can’t be pinched between the covers and the rails. On the bottom side of the PNA, carefully fold or push down the ribbon cables and wires so they can’t be pinched between the hardware and the outer cover.
Page 35
Description of the Upgrade Installation Procedure for the Upgrade Figure 20 Inner Cover Reinstallation Step 19. Reinstall the Outer Cover This procedure is best performed with the analyzer resting on its front handles in the vertical position. Do not place the analyzer on its front panel .
Page 36
Description of the Upgrade Installation Procedure for the Upgrade ④ 3. Install the four bottom feet (item ) onto the bottom of the outer cover ③ then install the foot locks (item ① ➁ 4. Install the strap handles (item ) by tightening the screws (item ) on both ends of each strap handle with a T-20 TORX driver.
Page 37
1. On the analyzer’s Help menu, click About Network Analyzer. 2. Verify that “224” is listed after “Options:” in the display. Click OK. If Option 224 has not been enabled, contact Keysight Technologies. Refer “Getting Assistance from Keysight” on page 4...
Page 38
Description of the Upgrade Installation Procedure for the Upgrade Step 22. Perform Post-Upgrade Adjustments and Calibration Adjustments The following adjustments must be made due to the hardware changes of the analyzer. — 10 MHz freq adjustment — EE default adjustment —...
Page 39
Description of the Upgrade Installation Procedure for the Upgrade — IF Response Adjustment (Options 090, 093, or 094 Only.) — Noise Adjustment (Option 029.) These adjustments are described in the PNA Service Guide and in the PNA on-line HELP. A list of equipment required to perform these adjustments is also found in the service guide.
Page 40
Description of the Upgrade Installation Procedure for the Upgrade Installation Note N5242-90003...