Tools and Equipment Required for the Installation
T-10 TORX driver (set to 9 in-lbs)
T-20 TORX driver (set to 21 in-lbs)
5/16-in torque wrench (set to 10 in-lbs)
5/16-in torque wrench (set to 21 in-lbs)
Use a 5/16-in torque wrench set to 10 in-lbs on all cable connections except the front and rear
CAUTION
panel cable connectors. Torque these connections to 21 in-lb.
ESD Equipment and Supplies Required for the Installation
ESD grounding wrist strap
5-ft grounding cord for wrist strap
2 x 4 ft conductive table mat and 15-ft grounding wire
ESD heel strap (for use with conductive floors)

Overview of the Installation Procedure

Step 1. Remove the Outer Cover.
Step 2. Remove the Front Panel Assembly.
Step 3. Remove the Existing Test Set Cables.
Step 4. Assemble the Mechanical Switches.
Step 5. Install the Mechanical Switches.
Step 6. Remove the A19 Test Set Motherboard and the A20 IF Multiplexer Board.
Step 7. Install the Bulkhead Connectors and Jumpers on the Rear Panel.
Step 8. Install the Bulkhead Connectors in the Test Set Front Plate (For Analyzers with Serial Numbers Prefixed
MY/SG/US5310 and Below).
Step 9. Install the New Test Set Cables.
Step 10. Reinstall the A20 IF Multiplexer Board and the A19 Test Set Motherboard.
Step 11. Reinstall the Front Panel Assembly and Front Panel Jumpers.
Step 12. Position the Cables and Wires to Prevent Pinching.
Step 13. Reinstall the Outer Cover.
Step 14. Enable Option 423.
Step 15. Perform Post-Upgrade Adjustments and Calibration.
Step 16. Prepare the PNA for the User.
Installation Note N5242-90005
Description
Description
Qty
Part Number
1
N/A
1
N/A
1
N/A
1
N/A
Keysight Part Number
9300-1367
9300-0980
9300-0797
9300-1308
7

Advertisement

loading

This manual is also suitable for:

N5249au- 927N5242au- 927N5242-60104