Huawei FusionModule2000 Installation Manual page 48

Smart modular data center, 2000 mm high cabinets, single-row aisle containment, 380 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
Store the removed transport fasteners. They should be reinstalled if the equipment needs to be
transported in future.
Figure 3-19 Removing the transport fasteners from a compressor
If the air conditioner is configured with no water pump, skip
If the air conditioner is configured with no water pump, do not connect the white terminal
reserved in the lower left part at the front of the air conditioner. If the air conditioner is
configured with a water pump, the white terminal has been connected before delivery.
Step 2 (Optional) Remove the liquid level detector transport fastener.
1.
Issue 04 (2017-06-30)
Open the front door, use a Phillips screwdriver to remove the four M4x10 screws from
the cover, and remove the cover, as shown in Figure 3-20.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation Preparations
Step
2.
39