Step 3: Connecting Power Optimizers in Strings

You can construct parallel strings of unequal length, that is, the number
of power optimizers in each string does not have to be the same. The
minimum and maximum string lengths are specified in the power
optimizer datasheets. Refer to the
 1. Connect the Minus (-) output connector of the string's first power optimizer to the
Plus (+) output connector of the string's second power optimizer.
 2. Connect the rest of the power optimizers in the string in the same manner.
WARNING!
If using a dual-input power optimizer and some inputs are not used, seal the
unused input connectors with the supplied pair of seals.
 3. If you intend to monitor the installation, using the monitoring platform, record the
physical location of each power optimizer, as described in Creating Logical and
Physical Layout using Installation Information on page 55.
StorEdge Three Phase Inverter Installation Guide MAN-01-00648-1.1
Figure 3: Power optimizer connectors
Designer
for string length verification.
Figure 4: Power optimizers connected in series
Chapter 2: Installing the Power Optimisers
    17