▷ We recommend installing a manual valve AKT 25
in the pipe leading to the safety relief valve
VSBV 25, so that the annual function check of
the safety shut-off valve JSAV can be carried out
without having to remove it.
▷ To prevent the VSBV from being unintentionally
shut off, we recommend removing the manual
valve lever after commissioning and attaching
it to the pipe.
JSAV

Connecting the impulse line

▷ The connection flange is suitable for an impulse
line with a pipe diameter of 8 mm.
1
2
3
4
▷ On the JSAV..T, remove the blind plug and con-
nect an NPT
1
/
impulse line.
8
5 Install the impulse line and seal with approved
sealing material.
▷ Ensure that there is sufficient tube length for the
impulse line.
JSAV
▷ Ensure that the valve seat of the JSAV is open,
▷ Note max. test pressure. JSAV inlet and outlet:
_ > 5DN
Push union
nut and
compression
fitting onto
the impulse
line.
_ > 5DN
GB-3

Tightness test

WARNING
An additional tightness test must be carried
out on the JSAV at all joints which have been
opened for maintenance work or replacement
of spare parts.
see page 5 (Resetting).
 Block the pipeline at the inlet and outlet.
max. 6 bar (87 psig), impulse line: max. 750 mbar
(10.9 psig).
 Slowly apply test pressure.
3
N
= max. 6 bar
2
4
N
= max. 750 mbar