Figure 12: Inserting The Chassis (Inner) Slide Rail Into The Cabinet (Outer) Rail; Figure 13: Mounting The Server Into The Rack Cabinet - Quanmax RAK-120S User Manual

Table of Contents

Advertisement

4. Make sure that the ball retainer is in fully open position. Then insert the chassis (inner) slide rail into the cabinet
(outer) slide rail.

Figure 12: Inserting the chassis (inner) slide rail into the cabinet (outer) rail

Retainer is in full open position
It is important to check if the ball retainer is in fully open position before installing the
server. It might cause catastrophic damage to the server chassis if ball retainer is not in fully
open position while mounting the server.
5. Release the slide from locking position by pressing the trigger down. Then Push the server back to the cabinet.

Figure 13: Mounting the server into the rack cabinet

6. After installation (or maintenance) is finished, it is suggested to secure the server by putting screw through the
center hole on the cabinet (outer) slide rails.
Release safety lock before mounting
Push the safety lock forward to secure
RAK-120S - User Guide, Rev. 1.0
Press trigger down to release
slides from locking
// 35

Advertisement

Table of Contents
loading

Table of Contents