CESI 8000 Plus High Performance Separation-ESI Module Site Planning Guide RUO-IDV-05-3345-C | B11953AF October 2018...
Page 2
SCIEX warranties are limited to those express warranties provided at the time of sale or license of its products and are SCIEX s sole and exclusive representations, warranties, and obligations.
Ventilation and Waste Collection Requirements......................16 Environmental Requirements............................16 BioSafety Requirements.............................17 Computer, Software, and Network Requirements......................17 Controller Requirements............................17 Printer Requirements..............................17 LAN Connection (Optional)............................17 Customer-Supplied Solutions and Equipment........................17 Site Planning Guide CESI 8000 Plus High Performance Separation-ESI Module RUO-IDV-05-3345-C | B11953AF 3 / 21...
Page 4
Customer Preparation Requirements..........................18 Mass Spectrometer Requirements (CESI-MS Systems Only).....................18 SCIEX Mass Spectrometers............................19 Thermo Scientific Mass Spectrometers........................19 Bruker Mass Spectrometers............................20 Waters Mass Spectrometers............................20 B Equipment Safety Categories.......................21 CESI 8000 Plus High Performance Site Planning Guide Separation-ESI Module 4 / 21 RUO-IDV-05-3345-C | B11953AF...
Complete the Site Planning Checklist on page 7 in consultation with facilities services personnel (electrical, ventilation, and information technology [IT]), and return it to the SCIEX field service employee (FSE) before the completion date. Refer to Signoff on page Note: The FSE will follow up if the checklist is not received prior to the scheduled installation date.
• Contact SCIEX Customer Service or the local FSE to schedule the installation. FSE Responsibilities Note: If the site preparation tasks are not complete when the SCIEX Field Service Employee (FSE) arrives, then the scheduled installation will be postponed. • Review the checklist and discuss outstanding issues with the site planner.
Customer Information Contact name Organization Address City ZIP code/Postal code State/Province/Region Country Telephone E-mail address Requirements Site Layout Refer to Site Layout Requirements on page Site Planning Guide CESI 8000 Plus High Performance Separation-ESI Module RUO-IDV-05-3345-C | B11953AF 7 / 21...
There is adequate lab space to accommodate the equipment. If the mass spectrometer inlet is lower or higher than the range of the CESI 8000 Plus cart, a table or stand of the appropriate height for the CESI 8000 Plus system is available.
(Optional) An active, tested LAN connection is available. Mass Spectrometer Requirements (CESI-MS Systems Only) If the CESI 8000 Plus system will be used stand-alone, then select the check box and do not complete the following table. Refer to...
All of the required solutions and bottles are available. Customer Preparation Refer to Customer Preparation Requirements on page Requirement Complete Up to two customers have been identified for familiarization. CESI 8000 Plus High Performance Site Planning Guide Separation-ESI Module 10 / 21 RUO-IDV-05-3345-C | B11953AF...
Site Planning Checklist Mass Spectrometer Information If the CESI 8000 Plus system will be used stand-alone, then select the check box and do not complete the following table. Mass spectrometer manufacturer Mass spectrometer model Mass spectrometer serial number Software version...
I acknowledge that all of the installation requirements, as specified in this document, have been met. Completion date Site planner signature (yyyy-mm-dd) FSE name Return date (yyyy-mm-dd) FSE e-mail CESI 8000 Plus High Performance Site Planning Guide Separation-ESI Module 12 / 21 RUO-IDV-05-3345-C | B11953AF...
• The location is away from vibrating equipment, such as refrigerators or centrifuges. • For configurations where the CESI 8000 Plus controller is connected to the mass spectrometer acquisition computer with a 4.3 m (14 feet) cable, the maximum distance between the controller and the acquisition computer is 4 m (13 feet).
Height Requirements (CESI-MS Systems Only) The alignment mark on the outside of the CESI 8000 Plus system is 36 cm (14 inches) from the bottom of the system. This mark must be vertically aligned with the mass spectrometer inlet. To align the two systems, the height of the cart provided with the CESI 8000 Plus system is adjustable.
Do not block the mains supply outlet. Mains Supply Fluctuations The CESI 8000 Plus system requires consistent voltage between 100 VAC to 240 VAC. Protective Earth Conductor WARNING! Electrical Shock Hazard. Do not intentionally interrupt the protective earth conductor.
Site Requirements Table A-1 CESI 8000 Plus High Performance Separation-ESI Module Electrical Specifications Specification Value Nominal input voltage Instrument: 100 VAC to 240 VAC, auto-ranging Cart: 100 VAC to 240 VAC, auto-ranging Controller: 100 VAC to 240 VAC Monitor: 100 VAC to 240 VAC...
Computer, Software, and Network Requirements Return to checklist. A computer (also referred to as a "controller") and monitor are supplied with the CESI 8000 Plus High Performance Separation-ESI Module system. Refer to the Site Planning Guide for the mass spectrometer for detailed requirements for the mass spectrometer acquisition computer.
Site Requirements Before the Installation Before the CESI 8000 Plus system can be installed, the mass spectrometer must be operational. To demonstrate this, a performance test should be performed and a printout of the results attached to this document. For some mass spectrometers, additional equipment is required, refer to the appropriate section below.
The OptiMS Bruker MS Adapter for Bruker Mass Spectrometers (PN B86099) requires the NanoElectrospray capillary cap set (PN 212915), purchased from Bruker. For Bruker mass spectrometers that are close to the ground, the CESI 8000 Plus system requires a low table or stand. Refer to Height Requirements (CESI-MS Systems Only).
Note: Environments with a Pollution Degree 2 rating include laboratories and sales and commercial areas. For more information, refer to the International Electrotechnical Commission standards IEC 61010-1 and IEC 60364. Site Planning Guide CESI 8000 Plus High Performance Separation-ESI Module RUO-IDV-05-3345-C | B11953AF...