Powercord; Inverter Paralleling Operation - Westinghouse iGen1200 User Manual

Digital inverter generator 1000 running watts, 1200 peak watts
Hide thumbs Also See for iGen1200:
Table of Contents

Advertisement

OPERATION
POWER CORD
Using Extension Cords
Westinghouse Portable Power assumes no responsibility for the content within this table. The use of this table is the
responsibility of the user only. This table is intended for reference only. The results produced by using this table are not
guaranteed to be correct or applicable in all situations as the type and construction of cords are highly variable. Always
check with local regulations and a licensed electrician prior to installing or connecting an electrical appliance.

INVERTER PARALLELING OPERATION

Never connect the paralleling cord
to the inverters with the inverters
running. The inverters must not be
running and both the paralleling cord
switches must be off when connecting
the cords.
WARNING
Do not use the paralleling cord for
any application other than inverter
paralleling. Do not use this cord on
other manufacturers' inverters.
Always ensure that both ends of
the paralleling cord are switched off
before connecting the inverters.
DANGER
INVERTER PARALLELING OPERATION
1. Using only the Westinghouse paralleling cord (Part
No. 260041) with both red cord switches set to
OFF (O), connect one male plug to one inverter and
connect the remaining plug into the other inverter.
Either of the receptacles on the inverters can be
used.
2. Start one of the inverters and wait until the output
ready light is on.
3. Turn both red cord switches to ON (I).
4. Start the remaining inverter; wait until the output
ready light is on before connecting the load.
5. When power is present, a light will illuminate in the
three-prong plug that is plugged into the inverter.
6. To stop the inverters, unplug all connected loads,
turn both cord switches to OFF (O) and unplug the
cord on each inverter.
7. If during operation the inverters' output is stopped
due to overloading, reduce the connected load by
unplugging appliances, and then push the reset
button and restart the inverter. When the ready light
is on, the load can be reconnected.
Westinghouse Portable Power | 11

Advertisement

Table of Contents
loading

Table of Contents