Advertisement

OPERATION
OPERATION
5. Pass wire ropes between the 1st and 2nd track rollers from the
front and between the 1st and 2nd track rollers from the rear.
However, for machines equipped with a full roller guard for the
track roller, pass the wire rope under the track.
6. Set the lifting angle (A) of the wire rope to 30° to 40°, then lift
the machine slowly.
7. After the machine comes off the ground, check the hook
condition and the lifting posture, and then lift slowly.
TRANSPORTATION
TRANSPORTATION
3 - 187