Quality Guaranteed; General; Individual Testing Reports - Saurya SLAM Hornet EM 1LED Instructions For Safe Use

Table of Contents

Advertisement

1.4

Quality guaranteed

1.4.1 General

®
The SLAM
Hornet series is designed, certified, manufactured and tested under ISO 9001:2008
quality system as well as additional requirements of the Directive 94/9/EC (ATEX) or IECEx scheme.
®
The SLAM
Hornet series is designed and tested according to the latest directives and standards. The
referred directives and standards of the production date in case are stated on the Declaration of
Conformity included in the delivery.

1.4.2 Individual testing reports

®
Each SLAM
Hornet unit has its own individual serial number and is provided with an original,
individual testing report when leaving the factory. The year of manufacture is specified on the type
label of the equipment. Following tests have been done for SLAM
standards relating to portable luminaries for explosion hazardous area. The Declaration of Conformity
is specifying the relevant standards. The testing report which is included in the delivery specifies the
results of the factory tests for that particular unit. The testing report typically specifies the following
tests:
PE –resistance test
The purpose of this test is to measure persistence of earth conductor.
Vital test for electrical safety as well as explosion safety because of e.g static electricity control.
The test current is 10 A (current) and the overall resistance should not exceed 0,5 W.
High voltage test (electrical strength)
The purpose of this test is to measure leakage current through insulation. Vital test for revealing
broken components or similar failures which can not be identified visually.
Testing voltage applied is 2130VDC. Maximum leakage current is 5mA.
Test of expected use of equipment
The luminary is subjected to shaking and vibration – to see that all the internal wires are properly
attached and components are not loose.
Operational test of luminaire and accessories
The unit is plugged-in and checked that it is working properly after all accomplished tests above.
Visual inspection
A final check to see everything is fine (screws attached properly, wires connected and required
markings attached).