Repair Report; Periodical Testing Of Shem; More Information About The Use Of Electrical Apparatus For Explosive Gas Atmospheres - Saurya SLAM Hornet EM 1LED Instructions For Safe Use

Table of Contents

Advertisement

·
High-voltage test (500 VDC between Phase & Neutral against P/E conductor)
·
Operational test
·
Test of expected use (vibrations, shaking)
Proper testing ensures safe operation of repaired equipment.
4.4

Repair report

The operator is responsible for keeping up to date record of the condition of his equipment (EN/IEC
60079-14). Ensuring the availability of this important information each repair procedure should be
written down in repair report according to EN/IEC 60079-19.
This report should reveal at least:
·
Person who conducted the maintenance
·
Date of maintenance
·
Procedure of maintenance
·
Signature of person responsible accepting the maintenance
4.5

Periodical testing of SHEM

Before test, allow battery to be fully charged. Operation of the battery must be checked 4 times a year
by cutting off the input voltage. Operation time in battery mode should be over 45 minutes. If not,
luminary is to be serviced.
4.6
More information about the use of Electrical Apparatus for
Explosive Gas Atmospheres
Please observe the requirements of the valid standards of the day. Please study at least the following
standards:
EN/IEC 60079-14 (Electrical installations in hazardous areas)
EN/IEC 60079-10 (Classification of hazardous areas)
EN/IEC 60079-17 (Inspection and maintenance of electrical installations in hazardous areas)
EN/IEC 60079-19 (Repair and overhaul for apparatus used in potentially explosive atmospheres)