III. Progress arrangement
The progress of the project should be arranged according to the preparation of the
project. A written plan should be worked out and submitted to the user for negotiation
and confirmation. The plan should include the following contents:
Delivery time and expected arrival time;
l
Date when engineers arrive the place of the user;
l
Progress arrangement of project installation and commissioning.
l

1.5.2 Kickoff Coordination

After arriving at the place of the user, the project supervisor should call a kick off
coordination meeting with the user. In this meeting, both parties should decide their
persons in charge, and achieve an agreement on installation period, project schedule
and cooperation matters.
1.6 U n p a c k i n g C h e c k
In the non-turnkey project, both the user and the project supervisor (engineer from
Huawei or cooperative party) are required to be present at the unpacking site. If one
party is absent at the unpacking site, another party who unpacks shall responsible for
any error occurring to the articles .
In the turnkey project, it is the project supervisor and the order management engineers,
who unpack, check & accept, hand over the articles, and make a confirmation with
signatures. The operation of Unpacking check and problem feed back in this case is
almost the same as that of the non-turn key project, except that the user does not need
to sign. The goods will be handed over to the user after passing the initial check of the
project.
The following will mainly deals with the former case.
Packi
g List
1.6.1
n
Before unpacking, both parties should check if the packing cases are damaged. If so,
stop unpacking and contact the order management engineer at the local office of
Huawei, waiting for the handling. Meanwhile, check if the quantity of cases on the site
agrees with the Packing List, and if the place of delivery agrees with the actual
installation place. If there is any disagreement, the project supervisor should feed back
the Article Problem Feedback Form confirmed by the user with a signature to the order
management engineer at the local office within 3 days.
After all the above inspections are ok, unpack the cases to check and accept the
articles.
 
Collation
1 -7