6.4 gauge pressure, absolute pressure from the differential pressure series and absolute pressure from the gauge
5. Open the shut-off valve
6. Open the shut-off valve for the process
6.4.2
Commissioning with steam or liquid
Requirement
All valves are closed.
Procedure
①
②
③
④
⑤
⑥
⑦
⑧
To commission the pressure transmitter for steam or liquid, proceed as follows:
1. Open the shut-off valve for the test connection
2. Via the test connection of the shut-off valve
start of scale value to the pressure transmitter.
3. Ensure that the lower range value corresponds to the desired value. Otherwise, correct the
value.
4. Close the shut-off valve for the test connection
SITRANS P320/P420 with 4 to 20 mA/HART
Compact Operating Instructions, 09/2018, A5E38874562-AB
⑥
at the pressure tapping point.
Pressure transmitter
Shut-off valve
Shut-off valve to process
Shut-off valve for test connection or for bleed screw
Pressure line
Shut-off valve
Drain valve
Compensation vessel (steam only)
③
.
④
.
②
, apply the pressure corresponding to the
④
.
Commissioning
pressure series
47