Quantech QCC3 Manual page 58

Air-cooled scroll compressor condensing units style a 80 – 160 ton 281 – 562 kw 60 hz r-410a
Table of Contents

Advertisement

FORM QCC3-EG1 (517)
Guide Specifications (Cont'd)
PART 3 - EXECUTION
3.01 INSTALLATION
A. General: Rig and Install in full accordance with Manufacturers requirements, Project
drawings, and Contract documents.
B. Location: Locate condensing unit as indicated on drawings, including cleaning and
service maintenance clearance per Manufacturer instructions. Adjust and level con-
densing unit on support structure.
C. Components: Installing Contractor shall provide and install all auxiliary devices and
accessories for fully operational condensing unit.
D. Electrical: Coordinate electrical requirements and connections for all power feeds with
Electrical Contractor (Division 16).
E. Controls: Coordinate all control requirements and connections with Controls Contrac-
tor.
F. Finish: Installing Contractor shall paint damaged and abraded factory finish with touch-
up paint matching factory finish.
58
QUANTECH

Advertisement

Table of Contents
loading

Table of Contents