Installation of RBS

5.1

Introduction

This document describes how to install the RBS 2308 and RBS 2309.
Target Group
The target group for this instruction is personnel involved in the installation of
an RBS.
5.2

Preconditions

This section provides preconditions that must be met before starting the
installation work.
Note: Specific preconditions exist for wall and pole mounting.
Documentation
This section presents additional documents required for the installation
procedure.
Ensure that the following documents are available:
General Preconditions
Before starting site work, ensure the following:
EN/LZT 720 0027 Uen R8A 2006-06-27
Completed and approved record prepared during site preparation
Site Installation Documentation (prepared by the Installation Engineering
department)
Standard Site Material Installation
Instructions
Site access permission received
Ordered RBS, equipment, specified tools and other necessary facilities
have been delivered
Site power is available
Site Grounding Point is available
RBS 2308 and RBS 2309 User's Guide
EN/LZT 720 0014