Installing the Switch using the N3K-C3064-ACC-KIT Rack-mount Kit
d) Tighten the 10-32 screws to 20 in-lb (2.26 N·m) or tighten the 12-24 screws to 30 in-lb (3.39 N·m).
Step 5
If you attached a grounding wire to the chassis grounding pad, connect the other end of the wire to the facility ground.
InstallingtheSwitchusingtheN3K-C3064-ACC-KIT Rack-mount
Kit
To install the switch, you must attach front and rear mounting brackets to the switch, install slider rails on the
rear of the rack, slide the switch onto the slider rails, and secure the switch to the front of the rack. Typically,
the front of the rack is the side easiest to access for maintenance.
Note
You must supply the eight 10-32 or 12-24 screws required to mount the slider rails and switch to the rack.
Before you begin
• You have inspected the switch shipment to ensure that you have everything ordered.
• Make sure that the switch rack-mount kit includes the following parts:
• The rack is installed and secured to its location.
Cisco Nexus 9348GC-FXP ACI Mode Hardware Installation Guide
18
• Front rack-mount brackets (2)
• Rear rack-mount brackets (2)
• Slider rails (2)
• M4 x 0.7 x 8-mm Phillips countersink screws (12)
Installing the Switch Chassis