APPENDIX D — REMOVE CONNECTIVITY COMMISSIONING (cont)
From the Setup Menu, select "Network". The PIC5 Net-
work Setup menu will display; see Fig. J.
Fig. J — PIC5 Network Setup
Verify that "Enable DHCP" is unchecked and Subnet mask
is set to 255.255.255.0.
Enter the supplied IP Address.
Save the changes.
Enter current Factory Password into PIC5, then go to Con-
figuration<Network Configuration and navigate to page 3 (see
Fig. K) using the bottom right hand arrow.
Fig. K — PIC5 Network Configuration Menu
In Network Configuration do the following:
• "Enable" BACnet/IP
• Verify that BACnet Metric Units is set to the default
"No"
• Type in the provided BACnet Identifier from the Cus-
tomer Gateway
After making these changes, save the changes and the PIC5
panel will cycle power automatically.
INADEQUATE SIGNAL STRENGTH
Sites with inadequate signal strength should work with Car-
rier Service for the best on-site solution to activate the remote
connectivity. Current alternatives to the standard antenna are a
higher gain antenna, AT&T signal boost device or installing a
Remote Connectivity Accessory box which is a separately
powered box that can be installed up to 100 m (330 ft) from
chiller.