Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 ® 585 Annubar Assembly Exploded View Nuts Remote Mount Instrument Connection Sensor Flange 585 Annubar Sensor Gasket Mounting Flange Assembly Studs Nuts Opposites Side Support NOTE Use an appropriate pipe sealing compound rated for the service temperature on all threaded connections.
Page 4
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 1: L OCATION AND RIENTATION Correct orientation and straight run requirements must be met for accurate and repeatable flow measurements. Refer to Table 1 for minimum pipe diameter distances from upstream disturbances.
Page 5
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 CONTINUED Upstream Dimensions Without Vanes With Vanes Out of Plane Plane A’ C’ — — — — — — — — — — NOTE • Consult the factory for instructions regarding use in square or rectangular ducts. •...
Page 6
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 CONTINUED Horizontal Orientation For proper venting and draining, the sensor should be located in the upper half of the pipe for gas applications. For liquid and steam applications, the sensor should be located in the bottom half of the pipe.
Page 7
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 CONTINUED Vertical Orientation The sensor can be installed in any position around the circumference of the pipe, provided the vents are positioned properly for bleeding or venting. Optimal results for liquid or steam are obtained when flow is up.
Page 8
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 2: D RILL OLES INTO 1. Determine the sensor size based on the probe width (see Table 2). 2. Depressurize and drain the pipe. 3. Select the location to drill the hole. 4.
Page 9
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 3: A SSEMBLE AND HECK For accurate measurement, use the following steps to ensure that Ports A and B are equal distances from the inside walls of the pipe. 1.
Page 10
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 4: W OUNTING ARDWARE 1. Center the flanged assembly over the mounting hole, gap in. (1,6 mm), and measure the distance from the outer diameter of the pipe to the face of the flange. Compare this to Table 3 and adjust the gap as necessary.
Page 11
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 CONTINUED 2. Place four -in. (6-mm) tack welds at 90° increments. Check alignment of the mounting both parallel and perpendicular to the axis of flow (see Figure 7). If alignment of the mounting is within tolerances, finish weld per local codes.
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 6: M OUNT THE RANSMITTER Transmitter Mounting, Direct Mount Head with Valves It is not necessary to retract the Annubar when direct mounting a transmitter with valves. 1. Place O-rings into grooves on the face of head. 2.
Page 13
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 CONTINUED 5. When impulse piping is longer than six feet (1.8 m) the high and low impulse lines must be positioned together to maintain equal temperature. They must be supported to prevent sagging and vibration.
Page 14
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 CONTINUED Recommended Installations Gas Service Secure the transmitter above the sensor to prevent condensable liquids from collecting in the impulse piping and the DP cell. Figure 9. Horizontal Gas Figure 10.
Page 15
Quick Installation Guide 00825-0100-4585, Rev AA Flanged 585 Annubar January 2009 CONTINUED Steam on Top Service Table 5. Steam on Top Temperature Limits Transmitter Connection Platform Maximum Temperature Remote Mount 850 °F (455 °C) Direct Mount 400 °F (205 °C) For remote mount installations the impulse piping should slope up slightly from the instrument connections on the Annubar to the cross fittings allowing condensate to drain back into the pipe.
Rosemount website at www.rosemount.com. A hard copy may be obtained by contacting our local sales office. European Pressure Equipment Directive (PED) (97/23/EC) Rosemount 585 Annubar — Refer to EC declaration of conformity for conformity assessment Pressure Transmitter — See appropriate Pressure Transmitter QIG...