5 Installing the Projector

Make sure to follow the steps below to install the wall mount. If you ignore these steps, the wall mount could
fall and cause personal injury or property damage.
Warning
When you mount the projector on the wall with the wall mount, the wall requires enough
strength to hold the projector and the wall mount, as well as the Control Pad and the
Touch Unit, if applicable.
This wall mount should be installed on a concrete wall. Confirm the weight of the projector
and the wall mount before installation, and maintain the strength of the wall. If the wall is
not strong enough, reinforce the wall before installation.
The maximum combined weight of the projector and the wall mount is about 44 lb (20 kg).
Do not hang cables over the wall mount.
Install the wall mount so that it can sufficiently support the weight of the projector and
wall mount, and resist any horizontal vibration. Use M10 nuts and bolts and make sure to
use appropriate wall anchors for your wall type. Nuts and bolts smaller than M10 could
cause the wall mount to fall.
Epson accepts no responsibility for any damage or injury caused by lack of wall strength or
inadequate installation.
A
Assemble the parts
1. Assemble the wall plate.
Assemble the wall plate and two frames into one unit, and secure them with the M4 × 12 mm hexagon
socket head cap bolts (×5) supplied.