Bottom Opening Duct Installation

1. Install gasket to duct flange to ensure air tight seal.
2. Install duct into place underneath framed opening in unit base per
Figure 60. Field-supplied duct connection to AHU bottom supply/return air opening
Trane AHU
base (typical)
Field-supplied
rigid duct
3. Bottom of unit base elevation is flush with duct opening in bottom of unit (see
CLCH-SVX07C-EN
curb layout provided with unit submittals for duct size and location.
Trane AHU
base (typical)
Figure
62).
Component Installation Requirements
Field-supplied
rigid duct
Figure
60. Refer to factory
Bottom
supply/return
airflow
Figure 61
and
73

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Performance Climate Changer and is the answer not in the manual?

Table of Contents

Save PDF