3.- COMMISSIONING AND OPERATION

3.1.- PRELIMINARY CHECKS BEFORE START UP.
1. Check that drain pipe connections, their fi xtures and that the level of the unit is tipped toward the drain.
2. Inspect the state of the ducts and grilles (clean and open grilles, no breaks in the duct, etc.).
3. Check that the power supply is the same as stated on the Rating Plate which is in agreement with the electrical dia-
gram for the unit and that cable sizes are correct. Check that tightness of the electrical connections to their terminals
and to ground.
4. Inspect the air fi lter, which should be in its housing and properly positioned (the metal grille should be toward the
inside).
FIGURE FOR THE STANDARD UNIT CONFIGURATION FOR PACKAGE MODELS
Legislation does not allow refrigerant gas emissions to the atmosphere, so the refrigerants have to be recycled
to avoid being released to the atmosphere. Those recycled refrigerants shall be processed afterwards by an
authorized waste manager.
Those components derived from the recycling of the unit have to be managed by authorized waste manager or be
left in local waste facilities according the local normative in each country.