Installation and Operation

SAW STAND SETUP

1. Remove the folding stand from its box (if available).
2. While holding the stand upright, spread both sets of legs
apart and swing the workbench over and on top of the
legs.
3. Insert lock pins through the legs and into the workbench.
Seat the saw securely onto the stand. (see fi gure 2)
Lock pin

BLADE INSTALLATION

(see fi gure 3)
1. Turn the two knobs on the inner blade guard coun-
terclockwise until the guard is free.
2. Pull the outer blade guard away from the inner blade
guard, away from the motor.
3. Remove the blade shaft nut and outer fl ange. If a blade
has been mounted, hold the blade with one hand and
use the other hand to loosen the nut with the included
wrench. Remove existing blade.
4. Mount new blade, but make certain the arrow on the
blade coincides with the rotation direction of the shaft.
5. Note if while loosening or tightening the blade the nut
turns independently from the blade, the other included
wrench must be used. Find the slot located behind the
inner flange on the blade shaft. Use second wrench to
hold blade/shaft in place and remove the nut.
fi gure 2

WATER PUMP INSTALLATION

1. Remove the water pump from the box and check that it
is not damaged (if not already installed).
2. Place the pump within the water tray such that the water
outlet is horizontal. (see fi gure 4)
3. Connect the water hose from the blade guard to the
pump and plug the pump's power cord into the recep-
tacle on the switch box.
4. Fill the water tray so that the water intake is fully im-
mersed. Proper water level must be maintained at all
times during saw operation.
Disconnect the pump before attempting to handle the
pump. Never operate pump without water in the tray.
fi gure 3
WARNING:
Knob
fi gure 4