8. Controller Test Procedure

8.1 Test Relays

"5. Test" in Main Menu
 "1. Relays" to test output
devices in the field (dry test)
 Highlight status, press ENTER,
"MAN" appears
 To end process press ENTER
again
For Irrigation valve test,
send someone out in field
with Walky-Talky to verify
status
Doc. Name: NMC-DC I
NOTE: In order to bring solenoid to Normally Open/Closed position either manually open
and close each output, or switch controller off and back on again for automatic positioning.
1
3
Output Level (A/D): ≤ 300 A/D
when all outputs are on.
If output level is above 300, see
Troubleshooting Appendix B
Installation Manual
Crop Management Technologies
INSTALLATION MANUAL
2
4
Revision: 01 I
Page:
39
of 109 pages

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Nmc-dc

Table of Contents