Parameterization of the Inverter Overview
Prerequisites:
Mechanical and electrical Installation are
completed.
Setting the supply frequency
DIP Switch 2: Off = 50 Hz / ON = 60 Hz
Power ON
Quick Commissioning P0010 = 1
See Chapter 5. For a lot of applications the inverter
will be ready.
Further Commissioning via P0004 and P0003
An overview about the parameter structure is given
on the right. A detailed description you will find in
the Operating Instructions and in the Reference
Manual.