Page 3
INTRODUCTION These machines, models B5, B10, B20 and B40 are coffee and tea brewing machines, with connection to the water mains. The machines are electronically controlled and work with a flow- through heater. Through the outlet in the swivel-arm hot water is guided into the filter unit where it filters through the coffee.
Page 4
Warnings ! For safe operation of the coffee brew 12. When the appliance has to be opened machine pay close attention to the following for repairs or maintenance, be sure to points: disconnect the electricity. 1. When the appliance is in operation, 13.
Page 5
(fig. 3). 5. Use the funnel supplied to pour water into the de-scaling aperture (fig. 8). The B5 and B10 models take 1,5 litres, the B20 takes 3,5 litres and the B40 4,5 litres. 6. The containers and filter units should be rinsed with hot water.
Page 6
OPERATION When using the machine keep the warnings When the fault occurs again or can not be from the INTRODUCTION in mind. corrected, contact your service engineer or 1. Put the plugs of the containers into the your dealer. sockets (no. 12, fig. 1) of the column. MAKING TEA 2.
Page 7
10 to 30 minutes. for accuracy. 6. Tip for getting rid of the cleaner solution: For B5 and B10: use 50 grams in 0,75 slide a hose pipe of sufficient length litre of water. For B20: use 100 grams and 1.8 cm diameter onto the drainage in 1,5 litres of water.
Page 8
9. After this time press the button for the When de-scaling twin-column models you next to largest quantity (no. 13.2, fig. 1). can use first one and then the other 10. Wait till the indicator light of the button container with filter unit so that the scale is goes out.
Page 9
MALFUNCTION ANALYSIS The following contains a list of malfunctions that you yourself may be able to resolve, along with the causes of the malfunctions and what may be done to rectify them. First consult this list before contacting your dealer or service engineer. If the malfunction does not appear in this list, or if the causes indicated are not applicable, please advice your dealer or service engineer.
Page 10
MALFUNCTION LIST OF THE CONTAINER Malfunction Possible cause: Solution: 1. The indicator lamp in Is electrical current Restore the connection to the switch does not present? the mains. (In the case of light up after the the column, insert the plug heating is switched of the container into the plug socket in the...
Page 11
COLUMN WITH COMPUTRONIC PANEL OPERATION OF THE TIMER Using the timer, up to four operational periods per day can be set, within which the machine will prepare coffee or tea. When a quantity is programmed with the selector buttons outside the set periods or blocks, the machine will only begin to work when the next block is timed to switch on.
Page 12
OPERATION Setting the timer is done as follows: 13. To set another block on the same day, 1. Ensure the timer is connected to the repeat instructions 9 through 12; to set a block on another day, follow instructi- mains supply and set selector switch (3, fig.
Need help?
Do you have a question about the B5 and is the answer not in the manual?
Questions and answers