7 Commissioning

6.4.5
To connect the electrical wiring on the
indoor unit
Electrical work should be carried out in accordance with the
installation manual and the national electrical wiring rules or code of
practice.
It is important to keep the power supply and the transmission wiring
separated from each other. In order to avoid any electrical
interference the distance between both wirings should ALWAYS be
at least 50 mm.
NOTICE
Be sure to keep the power line and transmission line apart
from each other. Transmission wiring and power supply
wiring may cross, but may NOT run parallel.
WARNING
Provide adequate measures to prevent that the unit can be
used as a shelter by small animals. Small animals that
make contact with electrical parts can cause malfunctions,
smoke or fire.
a
Terminal block
b
Electrical component block
c
Wire retainer
1 Strip the wire ends approximately 15 mm.
2 Match wire colours with terminal numbers on the indoor unit
terminal blocks and firmly screw the wires to the corresponding
terminals.
3 Connect the earth wires to the corresponding terminals.
4 Pull the wires to make sure that they are securely attached,
then retain the wires with the wire retainer.
5 Shape the wires so that the service lid fits securely, then close
the service lid.
6 Firmly fix the wires with the terminal screws.
7
Commissioning
7.1

Overview: Commissioning

This chapter describes what you have to do and know to
commission the system after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
7.2

Checklist before commissioning

Do NOT operate the system before the following checks are OK:
Installer reference guide
18
You read the complete installation instructions, as
described in the installer reference guide.
The indoor units are properly mounted.
The outdoor unit is properly mounted.
Air inlet/outlet
Check that the air inlet and outlet of the unit is NOT
obstructed by paper sheets, cardboard, or any other
material.
There are NO missing phases or reversed phases.
The refrigerant pipes (gas and liquid) are thermally
insulated.
Drainage
Make sure drainage flows smoothly.
Possible consequence: Condensate water might drip.
The system is properly earthed and the earth terminals
are tightened.
The fuses or locally installed protection devices are
a
installed according to this document, and have NOT been
b
bypassed.
The power supply voltage matches the voltage on the
c
identification label of the unit.
The specified wires are used for the interconnection
cable.
The indoor unit receives the signals of the user interface.
There are NO loose connections or damaged electrical
components in the switch box.
The insulation resistance of the compressor is OK.
There are NO damaged components or squeezed
pipes on the inside of the indoor and outdoor units.
There are NO refrigerant leaks.
The correct pipe size is installed and the pipes are
properly insulated.
The stop valves (gas and liquid) on the outdoor unit are
fully open.
7.3

To perform a test run

Prerequisite: Power supply MUST be in the specified range.
Prerequisite: Test run may be performed done in cooling or heating
mode.
Prerequisite: Test run should be performed in accordance with the
operation manual of the indoor unit to make sure that all functions
and parts are working properly.
1 In cooling mode, select the lowest programmable temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.
2 When the test run is finished, set the temperature to a normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.
3 The system stops operating 3  minutes after turning the unit
OFF.
7.3.1

To perform a test run in winter season

When operating the air conditioner in Cooling mode in winter, set it
to test run operation using the following method.
(A)(F)TXP20~35L2V1B + FTXF20~71A2V1B
Daikin room air conditioner
4P513661-1 – 2017.10