13. Switch off the injection current and check from the service menu readings of
thermal status and LOCKOUT that the lockout resets at the set percentage of
heat content.
14. Activate the cooling input signal to switch over to base current IBase2.
Wait 5 minutes to empty the thermal memory and set Time Constant 2 (Tau2)
in accordance with the setting plan.
15. Test with injection current 1.50 · IBase2 the thermal alarm level, the operate
time for tripping and the lockout reset in the same way as described for stage
IBase1.
16. Finally check that start and trip information is stored in the event menu.

Completing the test

Continue to test another function or end the test by changing the TESTMODE
setting to Off. Restore connections and settings to their original values, if they were
changed for testing purposes.
Breaker failure protection, phase segregated activation and
output CCRBRF
Prepare the IED for verification of settings outlined in Section
to verify
settings".
The Breaker failure protection, 3-phase activation and output function CCRBRF
should normally be tested in conjunction with some other function that provides a
start signal. An external START signal can also be used.
To verify the settings in the most common back-up trip mode 1 out of 3, it is
sufficient to test phase-to-earth faults.
At mode 2 out of 4 the phase current setting, IP> can be checked by single-phase
injection where the return current is connected to the summated current input. The
value of residual (earth fault) current IN set lower than IP> is easiest checked in
back-up trip mode 1 out of 4.
Checking the phase current operate value,
The check of the IP> current level is best made in FunctionMode = Current and
BuTripMode = 1 out of 3 or 2 out of 4.
1.
Apply the fault condition, including START of CCRBRF, with a current
below the set IP>.
2.
Repeat the fault condition and increase the current in steps until a trip occurs.
3.
Compare the result with the set IP>.
1MRK 505 372-UEN A
SEMOD53632-51 v5
"Preparing the IED
IP>
Busbar protection REB670 2.2 IEC
Commissioning manual
M12104-2 v12
M12104-23 v13

Advertisement

Table of Contents
loading

Table of Contents