Only qualified personnel must carry out the
commissioning and boiler operation as well
as the user instruction to prevent dangers
and injuries as well as material losses.
Commissioning gas train:
Prior to commissioning, ensure that the boiler corresponds
to the gas type available.
Gas type
Natural gas H
11.4 - 15.2
LPG P
20.3 - 21.3
- The boiler and system must be fully vented and must
be absolutely tight.
- If the system water pressure falls below 1.5 bar, top
up with water until a pressure of 1.5 to max. 2.5 bar
has been achieved.
- Check that all flue gas accessories have been correctly
installed.
- The gas fired boiler must be switched OFF. Open the
gas shut-off valve.
- Remove the casing cover.
- Release the plug at test nipple and vent the gas
supply pipe.
3062347_0309
Start-up gas connection
Wobbe index Ws
kWh/m³
MJ/m³
40.9 - 54.7
72.9 - 76.8
- Connect the hose to the pressure test appliance at
test nipple and check against atmosphere.
Gas type
Nominal supply pressure,
Permissible range
Natural gas H
20 mbar
LPG P
50 mbar
LPG P
37 mbar
LPG P
29 mbar
Never take the boiler into use if the actual value falls
outside the specified limits.
→ Notify gas supply utility.
- Read off value and enter in the commissioning
report.
- Pull the hose off and tighten the test nipple again.
- Retighten the plug.
- Start the boiler.
- Check the ignition and the regular flame structure of
the burner.
Check test nipple for gas-tightness,
otherwise gas may escape, resulting
in a risk of explosion, asphyxiation or
poisoning.
18 - 25 mbar
43 - 57 mbar
25 - 45 mbar
25 - 35 mbar