Figure 4. Two-post flush-mount installation
2
Attach one rail to the front post flange with two user-supplied screws, item 2.
3
Slide the plunger bracket forward against the vertical post and secure the plunger bracket to the post flange with two user-supplied
screws, see item 3.
4
Repeat this procedure for the second rail.

Two-post center-mount installation

NOTE:
For more installation instructions, see the installation labels attached to the rail assembly.
1
Slide the plunger bracket rearward until it clicks into place and secure the bracket to the front post flange with two user-supplied
screws, item 1.