6.3
Connecting supply and return lines
1.
Connect the supply line pipe (red label) with a flexible hose connection and with all the necessary compo-
nents, see Flexible hoses, Page 19.
2.
Connect the return line pipe (blue label) with a flexible hose connection and with all the necessary compo-
nents including a filter.
3.
Insulate the supply and return lines all the way to the heat pump.
1
2
Position
Description
1
Supply line (red)
2
Return line (blue)
6.4
Noise and vibrations
6.4.1
Installation of the heat pump
To prevent disturbing noise from the heat pump. the following recommendations should be observed:
•
In the event the heat pump is positioned on a vibration sensitive base, vibration dampers should be used. The
vibration dampers must be correctly dimensioned with regard to the heat pump's weight so that static spring
depression of at least 2 mm is obtained in all mounting components. Vibration dampers are available to pur-
chase as accessories.
•
Connection of the heat transfer fluid to the heat pump must be made using a flexible hose to prevent trans-
mission of vibration to building construction and the pipe system, see Flexible hoses, Page 19.
•
Ensure that pipes at lead-ins are not lying against the walls.
6.4.2
Flexible hoses
All pipes should be routed in such a way that vibrations cannot be transmitted from the heat pump through the
piping and continue into the building. This also applies to the expansion pipe. We recommend that flexible hoses
6 kW
DN 20
DN 20
Installation and service instructions VMGFI202 – 19
8kW
DN 25
DN 25