Establishing connection and verifying the IEC 61850 station communication
Section 4
4.1
4.2
Commissioning Manual
Establishing connection and verifying the
IEC 61850 station communication

Setting the station communication

To enable IEC 61850 station communication:
The IEC 61850-8-1 station communication functionality must be on in the
local HMI. Navigate to Main menu/Configuration/Communication/Station
communication/1:IEC61850-8-1 and set the parameter Operation to On.
To enable GOOSE communication the Operation parameter for the
corresponding GOOSE function blocks (GOOSEBINRCV and
GOOSEINTLKRCV) must be set to On in the application configuration.
To enable GOOSE communication via the front port the parameter GOOSE in
Main menu/Configuration/Communication/Station communication/
IEC61850-8-1 must be set to Front. To enable GOOSE communication via
rear port the parameter GOOSE must be set to LAN1.

Verifying the communication

Connect your PC to the nearby switch and ping the connected IED and the
Substation Master PC, to verify that the communication is working (up to the
transport layer).
The best way to verify the communication up to the application layer is to use a
protocol analyzer, for example, an Ethereal that is connected to the substation bus,
and monitor the communication."