Section 4
4.1 Initializing the instrument
System Startup
Important Note: The instrument only can work correctly if it is at
operating temperature. Let the instrument warm up for a minimum
of an hour so the inside of the enclosure, chemicals and electrode
are at operating temperature.
1. Make sure the PHOSPHAX sc is registered in the sc1000
2. Configure the analyzer in the SENSOR SETUP menu and note
3. From SENSOR SETUP, select
4. Select the PREPUMP ALL function and confirm.
5. Wait until the analyzer returns to the service state (displayed in
6. Select START from the maintenance menu.
system. If necessary, initiate the controller to search for the
analyzer. Refer to the sc1000 user manual for more
information.
the settings. Refer to
section 5.2 on page 35
information. The factory settings (default setting) are
appropriate for most typical applications.
PHOSPHAX sc>MAINTENANCE>TEST/MAIN.
TEST/MAIN.>PROCESS) after the prepumping sequence is
completed.
for more
33