Start-Up Procedures; General; Prime Condensate Trap With Water; Purge Gas Lines - Carrier 58MXA Installation, Start-Up, And Operating Instructions Manual

Deluxe 4–way multipoise fixed-capacity direct-vent condensing gas furnace
Table of Contents

Advertisement

NOTE: If TEST to C
terminals are jumpered longer than 2 sec,
OM
LED will flash rapidly, and retrieval request will be ignored.
5. When above items have been completed, the component test
sequence will occur as described in the Component Test
Sequence section above.
NOTE: Be sure to record the status code which is flashed 4 times
at start of component test for further troubleshooting.
6. After component test is completed and furnace is operating
properly, release blower access panel door switch, replace
blower access panel, and replace main furnace door.

START-UP PROCEDURES

Step 1—General
1. Furnace must have a 115-v power supply properly connected
and grounded. Proper polarity must be maintained for correct
operation.
NOTE: Proper polarity must be maintained for 115-v wiring. If
polarity is incorrect, control center LED status indicator light will
flash rapidly and furnace will not operate.
2. Thermostat wire connections at terminals R, W, G, and Y
must be made at 24-v terminal block on control center.
3. Natural gas service pressure must not exceed 0.5 psig (14-in.
wc), but must be no less than 0.16 psig (4.5-in. wc).
4. Blower access panel must be in place to complete 24-v
electrical circuit to furnace.
These furnaces are equipped with a manual reset limit switch
in burner box. This switch will open if an overheat condition
(rollout) occurs in burner enclosure. Correct inadequate
combustion-air supply or improper venting condition and
reset switch. DO NOT jumper this switch.
Before operating furnace, check each manual reset switch for
continuity. If necessary, press button to reset switch.
Step 2—Prime Condensate Trap With Water
Condensate trap must be PRIMED or proper draining may not
occur. The condensate trap has 2 internal chambers which can
ONLY be primed by pouring water into the inducer drain side
of condensate trap.
1. Remove upper inducer housing drain connection cap. (See
Fig. 42.)
2. Connect field-supplied 1/2-in. ID tube to upper inducer
housing drain connection.
3. Insert field-supplied funnel into tube.
4. Pour 1 quart of water into funnel/tube. Water should run
through inducer housing, overfill condensate trap, and flow
into open field drain. (See Fig. 43.)
5. Remove funnel and tube from inducer housing and replace
drain connection cap and clamp.
Step 3—Purge Gas Lines
If not previously done, purge lines after all connections have been
made and check for leaks.
Fig. 42—Inducer Housing Drain Tube
Fig. 43—Filling Condensate Trap
35
A99118
A99119