IV 5 – Installing the module – East West II
IV 6 – Fastening the module to the system
edge / expansion joint
IV 7 – Installation / ballast without
connection rail
Position the module on the base feet before placing
it on the module support set. Install the modules of
one axis of a double row first.
Place ballast in accordance with the ballast
planning into the base troughs after installing the
modules.
After fixing the modules place the support brace on
the module support set and fix the support brace to
the module support set. Support brace joint
overlapping above the module support brace.
Place ballast and install the modules on the other
side of the double row on the module support set.
- Wire adjacent modules when installing them
-
Install the string cable first
Place the drilling screw from the flat roof end clamp
centred over the screw channel of the base foot or
module support and screw in.
Tightening torque max. 6 Nm.
The screw must not be overtightened!
Approval from manufacturer required for clamping
in the corner section of the long frame side.
The amount of required ballast at the system edge
increases if not using a connection rail. No load
redistribution is possible.
The adjacent modules must each be secured with
the flat roof end clamp in the corner of the long
frame side instead of with the flat roof mid clamp.
Tightening torque max. 6 Nm.