Moving The Cabinet To The Installation Site - NEC Express 5800/320Fd Read Me First

Nec corporation of america servers owner manual
Table of Contents

Advertisement

If the corridor and door dimensions are large enough to
accommodate the unpacked cabinet still tied to its pallet, use a
pallet jack to move it from the delivery site to the installation site,
as described in
page
6.
If the corridor and door dimensions are too small to accommodate
the unpacked cabinet still tied to its pallet, unpack the cabinet and
unload it from the pallet before you move it to the installation site.
In this case, use the pallet jack to move the unpacked cabinet as
close to the installation site as possible. Then, unpack the cabinet,
remove it from its pallet, and roll it carefully on its casters to the
installation site.

Moving the Cabinet to the Installation Site

!
W A R N I N G
To avoid personal injury or damage to the
systems or cabinet, two persons are required
to move, unpack, and install a cabinet that
contains Express5800/320Fd systems.
Because of the size and weight of the systems
in cabinets, consider using professional
movers to deliver and move the packaged
units to the installation site.
!
C A U T I O N
To prevent or minimize condensation on the
systems' internal and external surfaces, avoid
exposing the systems to extreme temperature or
humidity changes when moving them to the
installation site. If the systems have been
exposed to extreme temperature or humidity
conditions during transit, or if condensation is
"Moving the Cabinet to the Installation Site"
-6-
on

Advertisement

Table of Contents
loading

This manual is also suitable for:

Express5800/320fd

Table of Contents